The GMC team has proven skills and experience to provide first-rate fabrication and installation of your most critical product lines. From clean planning to even cleaner execution, our collective expertise will take your project to the next level.
SIGMA ALDRICH
Objective: Pilot Plant
Timeline: 26 days, 12,000 man-hours
Conceptual Estimate: $1,350,000 – completed within 3% of the original budget
Project Overview: Fabricated and installed 16 modularized skids with piping, tanks, and pumps.